There are certain stages for obtaining Environmental Clearance for any project. These stages may be different for different project activities. The process of obtaining Environmental Clearance (EC) for the mining project involve following stages:
In brief;
The beginning of any project seeking environmental clearance starts with the filling of Form-I and Pre feasibility Report. There is a prescribed format of Form-I and PFR given on MoEF website. Filled application form (Form-I) along with PFR needs to be submitted at MoEF
After submission of Form-I and PFR, if the committee members find the feasibility of the project then they call the proponent for the TOR presentation. Either the lessee or an authorized person from the company must attend the presentation with all the documents and presentation copies or the consultant has to provide these things. TOR presentation is done in front of the various committee members.
If the committee members think that the project is feasible then they give the TOR points on the basis of which an EIA report will be prepared.
This is one of the basic but necessary point involve in every TOR. The baseline data will be collected for one full season (Non-monsoon). The secondary data are also collected for the particular area.
There is a prescribed generic structure of filling of a draft EIA report. There are 12 chapters included in any EIA report. The draft EIA report will be prepared after getting all the necessary details. These reports will be submitted to the respective Pollution Control Board of the respective city for the public hearing.
Public hearing is required to be done for involvement of local people to know whether they want the project activity to be executed or not. An executive summary in English as well as in the regional language is to be prepared along with the EIA report to be distributed among the local people of the respective area. Advertisement for the public hearing is given by the Pollution Control Board in the local newspapers. On the day of public hearing any local personnel can ask any question to the proponent of the project.
On the basis of the comments raised in the public hearing the draft EIA is revised again with the inclusion of the comments.
The duly completed report can be refer as a Final EIA report. Further it has to be submitted to the MoEF or SEAC.
There is a presentation of the EC in front of the committee members. Final presentation has to deliver in front of the committee members.
If the committee members conclude that the project activity is feasible and there will be no negative impact due to this activity on the environment, then they will grant environmental clearance to the project proponent. They may give certain suggestions to take into consideration by the proponent.
Know more about Mandatory EIA reporting: Sectors for which EIA is required to be done
Reference: Mr. Abhaya Garg
As the world continues to transition toward cleaner energy sources, the need for systems that can track, certify, and validate the renewable origin of electricity…
The carbon that marine ecosystems absorb and store is known as "blue carbon." The well-known idea of "green carbon," which describes the carbon retained by…
Introduction Soil testing is a crucial practice in modern agriculture. It assesses soil health, nutrient levels, and pH balance, enabling farmers to make informed decisions…
Ever wished your mobile phone could do more than just send memes and crush candies? Well, buckle up, because we're about to take your mobile…
As of 2023, 106 million people worldwide had bitcoins but the currency's influence on the environment is disproportionate. The primary method of cryptomining, known as…
In today’s modern world, where environmental issues are becoming more and more important, teaching kids to be environmentally conscious and eco-friendly is crucial to building…
View Comments
your analisis is very good
very good and useful