Electricity produced by Renewable Energy (RE) sources may conceptually be split into the pure electricity component and the “green” component. The “green” component is called as Renewable Energy Certificate (REC). One REC is equivalent to one megawatt hour of electricity generated from renewable energy sources. Generators of renewable energy have the option of selling the electricity along with the green component or selling only the pure electricity component and selling the RECs separately. Once REC component is commercialized, electricity component is considered to be a power from conventional sources.
Central Electricity Regulatory Commission (CERC) of India has enacted the regulations for REC mechanism in the country. State Electricity Regulatory Commissions (SERCs) of individual states have also formulated their own regulations on the basis of CERC regulations.
The title of CERC’s regulation is ‘Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010’.
These regulations specify the Terms and Conditions for Accreditation, Registration, Issuance and Trading of Renewable Energy Certificates in the country. The chronology of REC regulations is given below;
Stages involved;
Cost involved;
Cost required for REC project implementation as required by various government agencies is given in the tables below; (Note: Service tax has to be paid extra in all cases, information is as on April 2013).
Cost involved in Accreditation
Accreditation (State Agency) | Fees/ Charges (Rs.) |
Application Processing Fee | Rs. 5,000 |
Accreditation Charges (Onetime payment – valid for 5 Years) | Rs. 30,000 |
Annual Charges | Rs. 10,000 |
Re-validation fees (after 5 years) | Rs. 15,000 |
Cost involved in Registration
Registration (NLDC) | Fees/ Charges (Rs.) |
Application Processing Fee | Rs. 1,000 |
Registration Charges (Onetime payment – valid for 5 Years) | Rs. 5,000 |
Annual Charges | Rs. 1,000 |
Re-validation fees (after 5 years) | Rs. 5,000 |
Cost involved in Issuance
Issuance (NLDC) | Fees/ Charges |
Issuance fees | 10 Rs. per Certificate |
Cost involved in Trading
Trading (Energy exchange) | Fees/ Charges |
REC Trading – One time Portfolio Opening Charges at IEX | Rs. 40,000 * |
Note: *Charges applicable to IEX, Rs. /REC trading cost is also applicable. This is determined by respective power exchanges.
Registered capacity
There is total of 3,615 MW (by 09 June 2013) of renewable energy capacity registered under REC mechanism. The renewable energy source wise breakup is given in the following chart;
Source: REC registry website
Gardening is often thought of as just a way to beautify outdoor spaces. But can it affect more than the plants around you? Many people…
Sustainability in business-to-business (B2B) branding is no longer just about optics or surface-level commitments. Today’s buyers demand accountability, long-term thinking, and values-driven operations from their…
Integrated Pest Management (IPM) has gained considerable attention worldwide as a comprehensive, ecologically balanced approach to controlling insects, weeds, and diseases. Farmers, horticulturalists, and even…
Did you know that cinnamon comes from the inner bark of a tree? Yep! When it’s first harvested, it’s a light color, but as it…
Regenerative agriculture is an approach to farming that focuses on restoring soil health, enhancing biodiversity, and improving ecosystem functions. Unlike conventional farming, which often depletes…
Natural coral reefs and underwater habitats have been damaged by pollution, overfishing, and climate change. To help restore marine life, people create artificial reefs using…
View Comments