Renewable Purchase Obligations for the State of Maharashtra

Every Obligated Entity should have met its Renewable Purchase Obligations (RPO) target by their own generation or procurement of power from Renewable Energy generator or by the way of Renewable Energy Certificate or by the combination of all.

 

Obligated entities

  • Grid connected captive Power plant with minimum installed capacity of 1 MW and above
  • Entity with demand of minimum 1 MVA and who  consumes electricity procured from conventional fossil fuel based  generation through open access sources

Notes:

  1. These obligations shall be valid until March 31, 2016 (Financial year 2015-16).
  2. If the Obligated  Entity  fails to  comply with the RPO target- penalty amount for such conditions will be decided by the Commission on the basis of the shortfall in units of RPO, RPO Regulatory Charges and the Forbearance Price decided by the Central Commission;  separately in respect of solar and non-solar RPO

Installed power generation capacity and Renewable Purchase Obligations (RPO) to  the State of Maharashtra is given in following table;

 

 

Installed Capacity in MW of power utilities in Maharashtra/ UTS including allocated shares in joint & central sector utilities  (as on 31.3.10)

Thermal

Nuclear

Hydro

RE

TOTAL

14919

690

3332

2438

21379

Reference for the information: CEA Annual Report 2009-10 (Page number 212)

 

RPO Type

RPO by Year (%) – (Entity Type : DISCOM/Captive/OA)

2010-11

2011-12

2012-13

2013-14

2014-15

2015-16

Non-Solar

5.75

6.75

7.75

8.50

8.50

8.50

Solar

0.25

0.25

0.25

0.50

0.50

0.50

Reference for the information: Click here

 


Know more about the REC Mechanism

RPO for the state of Rajasthan

Read more on power supply position of the state of Maharashtra

18.52519973.848625
Shailesh Telang

Shailesh is post graduate in Environment Management from Forest Research Institute (FRI) University, Dehradun, India. Presently he is working in the areas of Environmental and Renewable Energy Advisory Services. He has started GreenCleanGuide.com during his college days.

View Comments

    • It's 6% of the quantity of power ditributed by MSEDCL for year 2010-11. Please see the graph (in post). I understand your question that you need exact RPO for the MSEDCL and it can be possible only if we have quantity of power distributed by it.

      • Yes Shyam, u r correct.. I need the MU distributed by..MSEDCL. I tried on their web site but cudn't get. Can u help me?

Published by

Recent Posts

Green Thumb, Marathi Style: Your Mobile’s Eco-Adventure Awaits!

Ever wished your mobile phone could do more than just send memes and crush candies? Well, buckle up, because we're about to take your mobile…

10 months ago

Environmental Impacts of Bitcoin and other Proof of Work (PoW) Mining Activities

As of 2023, 106 million people worldwide had bitcoins but the currency's influence on the environment is disproportionate. The primary method of cryptomining, known as…

11 months ago

Cultivating a Sustainable Future: Top Ten Green and Clean Habits to Teach Children

In today’s modern world, where environmental issues are becoming more and more important, teaching kids to be environmentally conscious and eco-friendly is crucial to building…

1 year ago

Top 10 House Plants for Clean Air

Our houses offer a safe haven from the outside world amid the chaos of modern life. However, common contaminants emitted by furniture, cleaning supplies, and…

1 year ago

The Environmental Impact of Scrap Metal Recycling

Scrap metal recycling stands as a cornerstone of sustainable waste management, playing a pivotal role in mitigating the environmental impact of metal production and waste…

1 year ago

Say Goodbye to Fuel Poverty by Applying For Free Energy Upgrades

If the worry of affording your next energy bill is giving you sleepless nights, you’re not alone. Millions of people in the UK have this…

1 year ago