Renewable Purchase Obligations for the State of Maharashtra

Every Obligated Entity should have met its Renewable Purchase Obligations (RPO) target by their own generation or procurement of power from Renewable Energy generator or by the way of Renewable Energy Certificate or by the combination of all.

Obligated entities

  • Grid connected captive Power plant with minimum installed capacity of 1 MW and above
  • Entity with demand of minimum 1 MVA and who  consumes electricity procured from conventional fossil fuel based  generation through open access sources

Notes:

  1. These obligations shall be valid until March 31, 2016 (Financial year 2015-16).
  2. If the Obligated  Entity  fails to  comply with the RPO target- penalty amount for such conditions will be decided by the Commission on the basis of the shortfall in units of RPO, RPO Regulatory Charges and the Forbearance Price decided by the Central Commission;  separately in respect of solar and non-solar RPO

Installed power generation capacity and Renewable Purchase Obligations (RPO) to  the State of Maharashtra is given in following table;

Installed Capacity in MW of power utilities in Maharashtra/ UTS including allocated shares in joint & central sector utilities  (as on 31.3.10)

Thermal

Nuclear

Hydro

RE

TOTAL

14919

690

3332

2438

21379

Reference for the information: CEA Annual Report 2009-10 (Page number 212)

RPO Type

RPO by Year (%) – (Entity Type : DISCOM/Captive/OA)

2010-11

2011-12

2012-13

2013-14

2014-15

2015-16

Non-Solar

5.75

6.75

7.75

8.50

8.50

8.50

Solar

0.25

0.25

0.25

0.50

0.50

0.50

Reference for the information: Click here


Know more about the REC Mechanism

RPO for the state of Rajasthan

Read more on power supply position of the state of Maharashtra

18.52519973.848625
Shailesh

Shailesh is post graduate in Environment Management from Forest Research Institute (FRI) University, Dehradun, India. Presently he is working in the areas of Environmental and Renewable Energy Advisory Services. He has started GreenCleanGuide.com during his college days.

Leave a Comment

View Comments

    • It's 6% of the quantity of power ditributed by MSEDCL for year 2010-11. Please see the graph (in post). I understand your question that you need exact RPO for the MSEDCL and it can be possible only if we have quantity of power distributed by it.

      • Yes Shyam, u r correct.. I need the MU distributed by..MSEDCL. I tried on their web site but cudn't get. Can u help me?

Published by

Recent Posts

Why tiny homes are the future of sustainable living

If you ask people what is that one thing they would like to have in their life. For many of… Read More

9 mins ago

June 2020: Monthly Environmental News Roundup

1. Hundreds of elephants dead in mysterious mass die-off A cluster of elephant deaths in the Okavango Delta was first… Read More

1 hour ago

June 2020: Monthly Electric Vehicle News Roundup

1-Apple's Upcoming Electric Vehicle Routing Feature Looks to End Range Anxiety Apple's iOS 14 system introduces a host of new… Read More

4 days ago

Five Electric Vehicles You Can Buy On Alibaba

The lockdown enforced by different countries across the globe in the wake of the Covid-19 pandemic has necessitated that we… Read More

7 days ago

Choose the Raine One for safer, faster and eco-friendly rides

As the world gravitates towards more sustainable transport options, electric scooters are gaining popularity fast for being easy to maneuver… Read More

7 days ago

Uttarakhand to Use Geotextile for Restoration of Bugyal

Permeable fabrics that have the capability to separate, filter, reinforce, protect, or drain when used in association with soil are… Read More

7 days ago